| Table VI-B: Commissioning status of Towers (IP-wise) as on 28.02.2010 in rural & remote areas for provision of Mobile Services | |||
| Name of Infrastructure Provider | No of clusters | Revised Number of Towers to be set up after dropping/ addition | Number of Towers Commissioned as on 28.02.2010 |
| RCIL | 5 | 407 | 396 |
| QTIL | 1 | 88 | 88 |
| GTL | 4 | 412 | 409 |
| KEC | 4 | 377 | 373 |
| BSNL | 63 | 5794 | 5481 |
| VODAFONE | 4 | 309 | 309 |
| TOTAL | 81 | 7387 | 7056 |